Gantt chart Target Date

I'm using the gantt chart, and I have values for a start and end date. I want to add a third field for a target date, and indicate that with some sort of marker - triange, circle, etc. Any suggestions?

Comments

  • I think that a target date would be a great feature request.

    Β 

    However, I have accomplished something similar to this by adding more stages (one for Plan and one for actual)1.png

    Β 

  • Update - AH, i see what you did. misunderstood at first. Thank you!

    Β 

    Is that what the red dot is? Your target date? Can you walk me through how you did that? That would be perfect for now!

    Β 

    On another note - how do we request features? New-ish to domo. Thanks!