Is there a way to add a date to workbench update
Is there a way to add a schema column for date for when the data was sent over?
From what I've seen, this is not possible, but there may be an optinon I missed or a workaround with SQL
For example, the Google Analytics connector adds a _BATCH_LAST_RUN_ column, which is similar to what I want but for workbench jobs. This would indicate when the data came through, which would be very beneficial for datasets without dates. I could use this date for trending analysis.
Say I have a dataset come through daily like this:
City | Count |
New York City | 2 |
The next day, it comes through like this:
City | Count |
New York City | 4 |
If I append the data, it will be like this:
City | Count |
New York City | 2 |
New York City | 4 |
There is no way to differentiate the days each row came through.
My ideal state would be every update, it would be something like this:
City | Count | Date |
New York City | 2 | 11/1/2016 |
New York City | 4 | 11/2/2016 |
Best Answer
-
You can use the Workbench transformations to add a column that inserts the current date. This should give you the date column you're looking to add.
1
Answers
-
Thank you @nicolasfeddern! I found it after poking around more.
Didn't know it was under the 'Calculated Field Transform' type.
1 -
Dani aka "Mr.Dojo"
Dojo Admin
**Say "Thanks" by clicking the "heart" in the post that helped you.
**Please mark the post that solves your problem by clicking on "Accept as Solution"
**You can update your Dojo Community name and avatar by clicking on your avatar then the "My Profile" button.0
Categories
- 10.8K All Categories
- 3 Private Company Board
- 1 APAC User Group
- 12 Welcome
- 39 Domo News
- 9.7K Using Domo
- 1.9K Dataflows
- 2.5K Card Building
- 2.2K Ideas Exchange
- 1.2K Connectors
- 343 Workbench
- 260 Domo Best Practices
- 11 Domo Certification
- 466 Domo Developer
- 50 Domo Everywhere
- 106 Apps
- 717 New to Domo
- 85 Dojo
- Domopalooza
- 1.1K 日本支部
- 4 道場-日本支部へようこそ
- 27 お知らせ
- 64 Kowaza
- 299 仲間に相談
- 654 ひらめき共有