Using date values for both x-axis and y-axis in chart
I have a dataset with a number of series (10-20) with two sets of dates that want to plot on both axis (see example below):
x-axis - update date (date a schedule was run to project anticipated finish dates - each series will have the same update dates)
y-axis - finish date (projected finish date for each series - date specific to each series and each update date)
Is there a way to produce this chart in DOMO? I've tried a few ways and DOMO indicates unable to process data.
milestone trend chart
Comments
-
First, I think this would be a great enhancement request. It doesn't look like it's currently possible to use a date value in both axes. That said, I have a potential, moderately tested workaround for you.
What I would do is create a new column that is a copy of one of the axes then convert it to a string. you could then use this to display the values and the original to sort and filter on.
Thanks,
Jake
**Say "Thanks" by clicking the "heart" in the post that helped you.
**Please mark the post that solves your problem by clicking on "Accept as Solution"1 -
I may be missing what you're trying to plot, but it sounds like a Gantt chart may work for what you want to visualize. This would give you a way of categorizing the series, and the chart will plot both the "start" and "end" dates of that series as a part of the project. Would that work for your needs?
Brett
**Say "Thanks" by clicking the "heart" in the post that helped you.
**Please mark the post that solves your problem by clicking on "Accept as Solution"1 -
Gantt chart works to visualize current schedule of tasks (one update) not to measure the trend of the completion of those tasks over multiple update periods. See image I posted originally for example.
1 -
Dani aka "Mr.Dojo"
Dojo Admin
**Say "Thanks" by clicking the "heart" in the post that helped you.
**Please mark the post that solves your problem by clicking on "Accept as Solution"
**You can update your Dojo Community name and avatar by clicking on your avatar then the "My Profile" button.0 -
Hi @Jaketh13 , I took your recommendation and cast the date into varchar in tSQL before bring in DOMO. After doing this and put this varchar date on y axis, DOMO shows me nothing. Any idea why it doesn't work?
1
Categories
- 11K All Categories
- 5 Private Company Board
- 2 APAC User Group
- 12 Welcome
- 43 Domo News
- 10K Using Domo
- 2K Dataflows
- 2.5K Card Building
- 2.2K Ideas Exchange
- 1.2K Connectors
- 349 Workbench
- 267 Domo Best Practices
- 12 Domo Certification
- 474 Domo Developer
- 51 Domo Everywhere
- 111 Apps
- 728 New to Domo
- 85 Dojo
- Domopalooza
- 1.1K 日本支部
- 4 道場-日本支部へようこそ
- 31 お知らせ
- 65 Kowaza
- 303 仲間に相談
- 664 ひらめき共有